Choosing a UPS rental requires more than finding a system with a kVA rating that appears larger than the equipment being supported.
The rental UPS needs to match the actual critical load, required kW and kVA capacity, input and output voltage, phase, battery runtime, generator configuration and temporary electrical setup.
For planned maintenance, equipment replacement, facility upgrades, emergency response or temporary capacity, establishing these requirements before selecting equipment can help narrow the available rental options and avoid problems during deployment.
CI Group maintains UPS rental systems across a broad range of capacities, including standard indoor equipment and self-contained outdoor UPS rental systems.
How Do You Size a UPS Rental?
UPS rental sizing begins with the load the temporary system actually needs to support.
Before reviewing rental equipment, determine:
- Critical load in kW
- Required kVA capacity
- Load power factor
- Input voltage
- Required output voltage
- Single-phase or three-phase configuration
- Required battery runtime
- Generator requirements, if applicable
- Redundancy requirements
- Indoor or outdoor placement
- Temporary connection and distribution requirements
These factors should be evaluated together. A UPS may have sufficient capacity but still be unsuitable if the voltage, runtime, phase or electrical configuration does not match the application.
1. Start With the Actual Critical Load
The first step is identifying what equipment the rental UPS is expected to support.
This is not always the same as the total electrical load of the facility.
During a temporary-power project, the rental system may support:
- An entire critical load
- One electrical distribution section
- A specific group of servers or IT equipment
- A process or production load
- A portion of a data center
- Equipment being transferred from an existing UPS
- Essential loads during maintenance or replacement
Where possible, use actual operating-load information rather than relying only on equipment nameplate ratings.
The project should also account for expected changes in load during the rental period. If equipment will be added, removed or transferred during the project, those changes should be included in the sizing plan.
2. Understand the Difference Between kW and kVA
UPS systems are commonly rated in kilovolt-amperes (kVA), while the equipment being supported may be described primarily in kilowatts (kW).
These values are related, but they are not interchangeable.
kW represents real power being used by the load.
kVA represents apparent power and accounts for the relationship between real power and the load’s power factor.
The basic relationship is:
kW = kVA × Power Factor
or:
kVA = kW ÷ Power Factor
For example, an 80 kW load operating at a 0.90 power factor represents approximately 89 kVA of apparent power.
That calculation is a starting point, not a complete equipment-selection decision. The UPS rating, operating margin, load characteristics, redundancy requirements and manufacturer specifications still need to be considered.
3. Do Not Size the Rental UPS From the Existing UPS Nameplate Alone
If a temporary UPS is being used during replacement or maintenance, it may seem easiest to simply rent a system with the same rating as the existing UPS.
That can be useful information, but it should not be the only sizing factor.
The existing UPS may:
- Be significantly larger than the current operating load
- Have been sized for expansion that never occurred
- Support loads that will not need temporary backup
- Have a different power factor rating than available rental equipment
- Use an electrical configuration that has since changed
Conversely, the facility may have added load since the existing UPS was installed.
Confirm the current load and electrical requirements before selecting the temporary system.
Match the UPS Rental to the Electrical System
4. Confirm Input and Output Voltage
Capacity alone does not determine whether a rental UPS will work with the facility.
The input and output voltage also need to match the temporary electrical design.
Common commercial and industrial UPS configurations can include voltages such as:
- 120V
- 208V
- 240V
- 480V
Some applications require the same input and output voltage, while others may involve transformers or other distribution equipment.
Before selecting a rental, confirm:
- Available source voltage
- UPS input voltage
- Required output voltage
- Load voltage
- Phase
- Frequency
- Existing transformer configuration, if applicable
A 480V UPS cannot automatically substitute for a 208V system simply because its kVA rating is appropriate.
5. Confirm Single-Phase or Three-Phase Requirements
Phase configuration also matters.
Smaller UPS applications may use single-phase power, while larger commercial, industrial and data center systems are commonly three-phase.
The rental UPS must be compatible with the available electrical source and the protected load.
This should be confirmed before equipment is shipped because changing the required electrical configuration at the project site can significantly affect the temporary-power plan.
6. Determine the Required Battery Runtime
UPS capacity determines how much load the system can support. Battery runtime determines how long the UPS can support that load from stored energy.
Those are separate requirements.
The appropriate runtime depends on what the UPS needs to accomplish during a power interruption.
For example, the batteries may need to provide enough time to:
- Bridge the load until a standby generator starts
- Allow transfer equipment to change power sources
- Complete an orderly shutdown
- Support a temporary operating procedure
- Maintain the load for a defined period without generator support
Runtime generally changes as the connected load changes, so a battery configuration that provides one runtime at partial load may provide a different runtime when the UPS is more heavily loaded.
CI Group’s UPS Battery Runtime Calculator can be used to estimate runtime based on UPS load, power factor, efficiency and battery configuration.
For data center applications, also see How Much UPS Battery Runtime Does a Data Center Need?
7. Decide Whether Redundancy Is Required
Some temporary-power projects require more than enough capacity to support the load.
They may also require redundancy.
Depending on the application, the temporary design could involve:
- A single UPS supporting the required load
- Multiple UPS modules sharing capacity
- An N+1 configuration
- Separate power paths
- Temporary bypass arrangements
Redundancy requirements should be established before selecting the rental equipment because they can change the number and size of UPS systems needed.
This is particularly important for data centers and other facilities where a temporary system still needs to support established availability requirements.
Coordinate the Rental UPS With Generators and Temporary Power
8. Determine Whether the Rental UPS Will Operate With a Generator
Many temporary UPS applications are part of a larger backup-power system that includes a generator.
In this arrangement, the UPS provides immediate power support while the generator starts and becomes available to carry the load.
The generator and UPS need to be evaluated together.
Project planning may need to account for:
- Generator kW and kVA capacity
- Generator voltage and phase
- UPS input requirements
- UPS efficiency
- Battery recharge demand
- Other loads connected to the generator
- Load sequencing
- Transfer equipment
- Generator frequency and voltage stability
For more information, see Can a Rental UPS Be Connected to a Generator?
9. Plan Bypass and Transfer Requirements
A rental UPS does not operate independently from the rest of the electrical system.
The temporary design may need to provide a way to safely move the load onto the rental system and later return it to the permanent power system.
Depending on the project, this may involve:
- Maintenance bypass equipment
- Temporary switchgear
- Automatic transfer equipment
- Manual switching procedures
- Temporary distribution equipment
- Planned maintenance windows
The switching sequence should be established before installation so the temporary system can be integrated without creating unnecessary downtime or operational risk.
10. Determine Whether the UPS Should Be Indoors or Outdoors
Not every facility has space available for temporary UPS equipment inside the building.
An outdoor UPS rental can provide another option when the project requires temporary critical power but available indoor electrical space is limited.
CI Group’s Outdoor UPS Rentals include self-contained configurations designed for temporary deployment outside the facility.
Outdoor deployment introduces additional planning considerations such as:
- Equipment placement
- Environmental protection
- Cooling
- Electrical connections
- Temporary cable routing
- Site access
- Security
- Clearances
- Delivery and removal
For a more complete review, see Outdoor UPS Rental Planning Guide: Placement, Cooling, Connections & Site Requirements.
Choose the Appropriate UPS Rental Capacity Range
Once the required load, electrical configuration and runtime have been established, the available rental inventory can be narrowed by capacity.
1–20kVA UPS Rentals
Smaller UPS rentals may be appropriate for localized critical loads, smaller IT environments, telecommunications equipment and other applications requiring limited temporary capacity.
21–160kVA UPS Rentals
This range can support larger commercial, IT and critical-power applications where temporary load requirements extend beyond smaller UPS systems.
161–550kVA UPS Rentals
Higher-capacity rental systems in this range can support larger commercial, industrial and data center loads during maintenance, upgrades or equipment replacement.
551–1200kVA UPS Rentals
Large critical-power applications may require rental UPS systems in the 551–1200kVA range, particularly where substantial facility loads need temporary protection.
Browse 551–1200kVA UPS Rentals
Outdoor UPS Rental Systems
When indoor placement is not practical, self-contained outdoor systems can combine UPS equipment and supporting infrastructure in a temporary outdoor configuration.
For requirements above these ranges or projects involving multiple UPS systems, the temporary-power design may need to be developed around several pieces of equipment rather than a single rental unit.
Information to Gather Before Requesting a UPS Rental
Providing complete project information helps narrow equipment options more quickly.
Load Information
- Current critical load in kW
- Required kVA capacity
- Power factor
- Peak expected load
- Type of equipment being supported
- Expected load changes during the rental period
Electrical Information
- Input voltage
- Output voltage
- Single-phase or three-phase
- Frequency
- Existing electrical distribution
- Transformer requirements
- Temporary connection requirements
Runtime and Backup-Power Information
- Required battery runtime
- Generator availability
- Generator capacity
- Expected generator start and transfer sequence
- Redundancy requirements
Project Information
- Project location
- Required rental start date
- Expected rental duration
- Indoor or outdoor placement
- Reason temporary UPS capacity is required
- Available installation space
- Delivery access
- Electrical one-line or project specifications, if available
If the project is part of a data center upgrade or replacement, see Can a Rental UPS Be Used During a Data Center Upgrade or Replacement?
Common UPS Rental Sizing Mistakes
Using kW and kVA as if They Are the Same
A load described in kW cannot automatically be matched to the same numerical kVA rating without considering power factor and the UPS manufacturer’s ratings.
Sizing From the Existing UPS Without Checking the Current Load
The existing UPS nameplate is useful information, but the facility’s present operating load may be significantly different from the load the system was originally designed to support.
Ignoring Battery Runtime
A UPS with sufficient capacity may still fail to meet the project requirements if its battery configuration cannot provide the required runtime.
Choosing the Right Capacity but the Wrong Voltage
Capacity does not correct an electrical-configuration mismatch. Input voltage, output voltage and phase need to be confirmed separately.
Forgetting Generator Coordination
If the rental UPS will operate from a standby generator, the generator and UPS should be evaluated as a combined system rather than selected independently.
Waiting Until Delivery to Plan Connections
Temporary cabling, switchgear, bypass equipment and connection points should be planned before the rental equipment arrives at the site.
Ignoring the Installation Environment
Indoor space, cooling, outdoor placement, weather protection, cable routing and site access can all affect which rental configuration is practical.
Does Rental Duration Affect UPS Sizing?
The length of the rental does not normally determine the electrical capacity of the UPS, but it can affect the overall project plan.
A system needed for a short emergency response may be deployed differently from equipment supporting a multi-month infrastructure replacement or construction project.
Rental duration can influence:
- Equipment availability
- Battery maintenance planning
- Temporary cabling and installation approach
- Site access requirements
- Service and support planning
- Overall rental cost
See How Long Can You Rent a UPS System? for additional information.
How UPS Size Can Affect Rental Cost
UPS capacity is one factor that can influence rental pricing, but it is not the only one.
The total project can also depend on:
- Required battery runtime
- Voltage configuration
- Transformers
- Outdoor or self-contained equipment
- Temporary distribution
- Cabling
- Freight
- Rental duration
- Installation requirements
- Project location
For a more complete discussion, see How Much Does a UPS Rental Cost? What Affects Temporary UPS Pricing.
Related UPS Rental Posts & Resources
How Much Does a UPS Rental Cost? What Affects Temporary UPS Pricing
Learn which equipment, runtime, installation, freight and project requirements can affect temporary UPS rental pricing.
Outdoor UPS Rental Planning Guide: Placement, Cooling, Connections & Site Requirements
Review what should be planned before deploying a self-contained outdoor UPS rental system.
When Does a UPS Rental Make Sense?
Review common situations where temporary UPS equipment can support maintenance, upgrades, replacement and other critical-power projects.
How Do You Size a Rental UPS System?
Get a shorter answer to the key load, kVA, voltage and runtime information needed when evaluating a rental UPS.
Can a Rental UPS Be Connected to a Generator?
Learn what needs to be considered when temporary UPS equipment will operate as part of a generator-backed power system.
How Long Can You Rent a UPS System?
Review how emergency, short-term and longer infrastructure projects can affect UPS rental duration.
UPS Battery Runtime Calculator
Estimate UPS battery runtime using the connected load, power factor, efficiency and battery configuration.
Need Help Sizing Temporary UPS Equipment?
The correct UPS rental should be selected around the complete temporary-power application—not a single kVA number.
Before equipment is selected, confirm the critical load, kW and kVA requirements, power factor, input and output voltage, phase, required battery runtime, generator configuration, redundancy requirements and installation environment.
If outdoor placement is required, review CI Group’s Outdoor UPS Rental systems and the Outdoor UPS Rental Planning Guide.
